SUMMARY
Challenge
n
To provide a variety of tenants with fluent access to
their offices while guaranteeing efficient access
control in a busy office hub
n
Elevator capacity had to be maximized without
sacrificing an inch of office space
Solution
n
Elevators equipped with a Destination Control System
and integrated PFI solution with access control to
prevent unauthorized entry
• Close collaboration with the architects at a very early
stage of the project to plan the layout of the elevators
inside the building
FAST FACTS
FIRST Rotterdam
n
Completed: 2015
n
Height: 120 m
n
Floors: 30
n
Architect: De Architecten Cie
n
Building owner: KONE
n
Developer: MAB Development
n
Contractor: Boele & van Eesteren
KONE Solutions
n
13 KONE 700 elevators with a
max travel of 115m and 6m/s
3 KONE Turnstile 100 with
KONE Polaris™ DCS and KONE
E-Link integration
n
KONE Polaris™ Destination
Control System with
touchscreens
n
KONE E-Link™ monitoring
system
n
1 hermetic KONE/Markus door
© Ossip Van Diuvenbode