31
SUMMARY
Challenge
■
Tomeet a tight delivery schedule ina complicated
and challengingdevelopment
■
To install elevators that canbeused tomovepeople
andmaterials efficiently and safely during the
constructionprocess
Solution
■
Providing the contractor with construction time
elevators toensureproject completionwithmaximum
efficiency
■
Setting safety as thehighest priority and ensuring
flexibilityandcooperationwith themultiplepartners
throughout thedevelopment process
FAST FACTS
GateTowers
■
Completed: 2013
■
Height: 238m
■
Floors:Towers3,4,5–68floors;
Tower7–23floors;
Basement +podium–6floors
■
Buildingowner: Aldar Properties
■
Developer: Aldar Properties
■
Architect: Arquitectonica
■
Architect of record:M/SKhatib
&Alami
■
Main contractor: Arabian
ConstructionCompany (ACC)
KONESolutions
■
27KONEMiniSpace
™
elevators
■
11KONEMonoSpace
®
elevators
■
3KONETranSys
™
freightelevators
■
4KONETravelMaster
™
escalators
■
15construction timeelevators
■
KONEE-Link
™
monitoring system