SUMMARY
Challenge
■
Toensure the smooth flowof residents and visitors
withpermanent vertical transportation solutions
that also facilitate the constructionprocess
■
To install unconventional elevator shafts in a twisting
buildingprofile
Solution
■
StrongcooperationbetweenKONEandotherpartners
throughall developmentphases
■
Providingconstruction timeuseof permanent elevators
for anextendedperiod toensureefficient completion
of interior finishes
■
Circular elevator shaftspositioned in thecenterof the
building to suit thehelical design
FAST FACTS
CayanTower
■
Completed: 2013
■
Height: 306m
■
Floors: 75
■
BuildingOwner: CayanGroup–
Real Estate Investment&
Development
■
Developer: CayanGroup–
Real Estate Investment&
Development
■
Architect: SOMSkidmore,Owings
&Merrill LLP
■
Contractor: ArabtecConstruction LLC
KONESolutions
■
7KONEMiniSpace
™
elevators
■
1KONEMonoSpace
®
elevator
■
KONE InfoScreen
©CayanGroup